Heathrow Airport was warned about the "resilience" of its power supply in the days before a fire which shut down the airport ...
The official told a parliamentary committee that he had raised concerns about the resilience of Heathrow’s electricity supply ...
Airlines warned Heathrow airport about concerns over the resilience of its electricity supply days before a power outage ...
The boss of Heathrow came under fire for an 18-hour shutdown at the airport last month after an airline representative said ...
The boss of Heathrow Airport has apologised to the over 200,000 passengers whose journeys were disrupted by its closure last ...
In 2024, Heathrow was the busiest airport in Europe by passenger numbers and the fourth busiest worldwide. Nearly 84 million ...
Britain's aviation watchdog will consider Heathrow airport's resilience rules as part of a regular review, it said on ...
Heathrow Airport faced severe disruptions on 21 March after a power substation fire led to a near 24-hour shutdown, impacting ...
The Independent estimates the total cost to airlines at Heathrow as £100m in lost revenue and passenger care expenses ...
London Heathrow Airport was warned about possible issues with its power supplies a few days before a nearby fire cut ...
Heathrow – the UK’s and Europe’s busiest airport – closed for hours until about 6pm on Friday while thousands of homes were ...
It could cost $100 million and take years to install the backup generators to prevent another hourslong power loss like the ...